Read on below for updates on exciting projects coming to Wornall Rd. in 2024!

(This page will be constantly monitored and updated). Last update: 3/24/2024

 

74th St.-79th St. Wornall Rd Reconstruction:

Project Contacts:

Wornall Road Improvements:

Randy Alewine, Project Manager
816-513-2589
Courtney Stephens, Public Information Officer
Jason Waldron, Transportation Director
816-799-4792
Jerald Stevens, KC Water
816-513-0446
Tim Hutson, KCMO Public Works Project Superintendent
74Broadway (EPC Real Estate Group Development):
Jeremy Tinkler
816-405-5958
Austin Bradley
913-558-1014

Construction Update:

(4/12/24 Update)

Work will begin on the South lot at the corner of 75th and Wornall on 4/22.

As the North lot is finished, it will open for parking for patrons.

No new word on the EPC apartment build at this time.

(3/22/24 Update)

Wornall Reconstruction:

The North lot at 74th St. should be complete within the next three weeks. South lot next.

KCATA Bus pick-ups will be moving from Topsy’s on 74th Terrace to another location close by.

The CCVI Trolley Run will now begin at 73rd St./Wornall instead of 75th St. on Sunday, April 28th.

74Broadway:

New amenities have been introduced for the project’s future community, which include a wine/whiskey lounge, indoor golf simulator, a state-of-the-art fitness center, and more.

The plans now are to begin clearing the site in April with a June start date for construction.

(3/11/24 Update)

Trolley Track Trail detour expected until June 2024.

Broadway from 74th to 74th Terrace is estimated to be closed until 2026 for property development within the project footprint.

Wornall Project underway with a projected completion Fall 2025. Please be aware of vehicle and mobility detour signage.

(2/28/24 Update)

Work has begun to replace the water main located underneath Wornall Rd. from 72nd St. to 75th St. Traffic is now single lane going North/South and will eventually close entirely for several weeks to finish.

(2/23/24 Update)

74Broadway Update:

Currently allowing City to use properties surrounding the former Well for material storage.

Plan to clear site in April, start construction in May 2024.

Utilities currently being set up.

(2/21/24 Update)

Wornall Reconstruction:

Parking for businesses located at the NE corner of 75th/Wornall has been severely impacted by KCATA bus route shift/construction work.

Construction crews have been instructed to cease parking in South Broadway lot/in front of Collar Club.

Work moving ahead as scheduled.

(2/13/24 Update)

Work has begun on the North ATA Parking lot directly across from former Well site. Work on this lot and the south adjacent lot is expected to last through the end of April 2024.

The KCATA bus stop formerly located on Broadway has moved down the street in front of Topsy’s (221 W 74th Terrace).

The 74th Terrace entrance to parking lots is now a one-way entry.

Parking will get more difficult before the completion of the project–please be courteous to our local businesses when leaving cars in the lot.

(1/22/24 Update)

(1/20/24 Update)

Weather permitting, work on the North ATA lot at 74th/Wornall will begin 1/21/24.

(11/27 update)

Work will begin on the project early 2024 and is expected to be completed within 15 – 18 months.

(10/19 update)

Three bids were received 10/3/23 for the work to be done along Wornall Rd. KCMO intends to make a decision on the bids the week of 10/23/23. Work plans will be released to the public by their PI team soon after.

Projected Upcoming Construction Phases

Phase 1A and 1B: January – April
Phase 2: March – May

Phase 3: May – October

 

Project Description:

Wornall Road is just east of Leawood and runs parallel to the Missouri/Kansas border. This project will reconstruct Wornall Road from 74th Street to 79th Street. Roadway improvements include:

  • Newly reconstructed roadway
  • Trolley Track Trail extension from 74th to 75th Street
  • Improved traffic flow
  • Pedestrian accommodations
  • Parking lot modifications at 75th and Wornall Rd.
  • New, interconnected signals
  • Coordination with the KCMO Smart Sewer Program– Green Infrastructure
  • New sidewalk along 79th St.
  • New LED streetlights
  • Water main replacement on Wornall Rd. from 75th to 77th Street

Background

In 2015, the City and the Waldo Community Improvement District conducted an assessment of the intersection of 75th Street and Wornall Road in order to evaluate traffic capacity, safety, and walkability of the intersection. The study resulted in recommendations that are aimed to improve traffic flow, while at the same time improve the intersection so that it incorporates features to improve pedestrian friendliness. The study also identified ways to extend the Trolley Track Trail between 74th Street and 75th Street, thereby eliminating a major barrier for pedestrians and bicyclists.

Since that time, the City, working with the Waldo CID, has received a $2 million grant to implement the results of the study. The City has appropriated funds for the reconstruction of curbs and sidewalks along Wornall Road from 74th and 75th Street. Given the extensive work proposed, the City is now aiming to completely reconstruct Wornall Road from 74th Street to 79th Street, a stretch of roadway that is well worn and beyond ordinary maintenance. This is significant work that, when completed, will improve this key commercial corridor within Waldo.

Traffic Impact:

Traffic will continue to be impacted throughout the entirety of the project.

 

 

EPC “74Broadway” Development:

Project homepage

EPC Real Estate Group, in conjunction with PortKC, will be beginning work on their proposed “74Broadway” development in the fall of 2023. In total, the development will contain:

  • 278 units, including 56 affordable units at 60% MFI.
  • 364 structured parking stalls.
  • 29 surface parking stalls.
  • 17,500 sq. ft. of retail/dining space.

Construction Phase:

10/23 UPDATES (more included above):

  • EPC has closed on the properties located between 74th St. and Terrace along Broadway.
  • EPC currently solidifying bids for demolition and utility relocation
  • The Well auction closes Monday afternoon, 10/23. Auction winners will have thirty days to remove items from property.
  • Still expecting a Q4 2023 demolition and Q1 2024 construction start.
  • EPC will begin with parking garage so as to have a completed storage space for materials throughout length of build.